| Portable Building
Installation
Installing a portable building
at your site requires a close working relationship with
all parties involved in the project to ensure that the portable buildings
is delivered and fully operational within the agreed time
scale.
Typically a temporary building can be delivered &
installed within days of order.
Initially a detailed site survey will be carried out to
determine the structure fits the sites configurations. Ground
conditions will be assessed which will determine the type
of anchorage used to fix the structure securely to the ground.
An underground services scan will be conducted to check
for gas pipes and electrical wires are not directly under
the proposed site for the portable building.
On delivery of the portable building
the A Frame is built on the ground and once complete this
is lifted into position using a telehandler and scissor
lift. This is then locked into position using a diagonal
bracing bar before the next A Frame is lifted in position.
On completion of the portable building the Roof and Diagonal Wall bracings and purlins
are fixed into position securing the first 2 A frames into
position.
The above procedure is then carried out until the structure
is complete. At this stage the roof, walls, Roller Shutter
Doors and Pedestrian Doors will be installed.
To ensure crew and site safety the crew are supplied with
the correct protective equipment from hard hats, steel capped
boots and harnesses for the scissor lift.
A detailed Method Statement and Risk Assessment are sent
to the client prior to delivery of the portable temporary building.
|